Heidelberg Water Upgrades

Project number: 04194 |  Updated: February 2025

The Region of Waterloo is upgrading the water supply system in the community of Heidelberg in Wellesley. This work includes constructing a new watermain along Lobsinger Line from St. Clements to Heidelberg that will connect to the St. Clements Water Treatment Plant. Service connections will be made to unserviced properties along Lobsinger Line in Heidelberg.

The existing Heidelberg Water Treatment Plant is no longer in use and will be demolished in 2025.

Schedule

Environmental assessment: 2022
Construction: June–September 2024
Surface paving: Spring 2025

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget

$1,689,700

Contact

Padraig Keating, P.Eng.
Project Manager, Region of Waterloo
pakeating@regionofwaterloo.ca 

Service First Contact Centre: 519-575-4400; for deaf and hard of hearing (TTY) call 519-575-4608

Getting around during construction

Lobsinger Drive and Kressler Road are back open. Stay tuned for updates on surface paving construction impacts in spring 2025.