William Street Water Supply System

Project number: 04160 |  Updated: January 2025

The Region of Waterloo is improving the William Street Water Supply Systems in Waterloo. This project includes the construction of a new well house, drilling a new well, removing the existing reservoir and wellhouses and removing the old equipment in the existing pumping station. Once the project is complete, water from this well field will be sent to the Strange Street Water Treatment Plant for treatment and distribution.

This project will improve the water quality and reliability in the Region and reduce operations and maintenance costs.

Schedule

Environmental assessment: 2018–2021
Design and planning: 2022
Construction: May 2023–July 2025

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget

$13.3 million

Contact

Andrew Calder, P.Eng
Project Manager, Region of Waterloo
AMCCalder@regionofwaterloo.ca 

Service First Contact Centre: 519-575-4400; for deaf and hard of hearing (TTY) call 519-575-4608

Contractor

May to November 2023: Well Initiatives
Current: H2Ontario

Getting around during construction

William Street is back open with no future closures needed for this project. The construction is now within the supply system site.


Project details

Project studies and resources

Contact Us

Region of Waterloo General Inquiries
150 Frederick St., Kitchener, Ontario N2G 4J3

Phone: 519-575-4400
Deaf and Hard of Hearing (TTY) : 519-575-4608
Email the Region of Waterloo General Inquiries
Link to Region of Waterloo Home Page
Map this Location.